Cuyamaca College Business / CIS Building
 
Business/CIS Building
Project Overview
:
The Business/Computer Information Systems Building will address the shortage of laboratory space that currently exists with the business program. It will provide facilities for CIS labs, Economics/Real Estate, Business Office Technology, Paralegal and CIS computer labs. The building will be located Northwest of the LRC and North of the Building A thru G complex.
   
   
Project Description:
Project Name: Business / CIS Building
Building S.F.: 50,570 GSF / 33,245 ASF
Total Labs/Classrooms: 19 Labs / 1 Classroom – Final Mix to be Determined
Gross Seats: 785
Funding: Combination of State Funding and Prop. R
Project Type: New Construction
Est. Project Cost: $28 million
 
   
Project Team:
Program Manager: Jim Davies
Senior Project Manager: Jack Miller
Project Manager: Bill Dos Santos
Architect: LPA, Inc.
Construction Manager: Rudolph and Sletten, Inc.
 
   
Project Timeline:
IPP  
Board Approval:
Completed
State Approval:
Completed
FPP  
Board Approval:
Completed
State Approval:
Est. November, 2006
PP  
Board Approval:
Est. April, 2007
State Approval:
Est. May, 2007
WD  
District Approval:
Est. January, 2008
State Approval:
Est. February, 2008
Issue for Bid
Est. May, 2008
Construction  
Start:
Est. June 2008
Complete:
Est. Spring 2010
 
   
Legend:
IPP: Initial Program Proposal - programming
FPP: Final Program Proposal - conceptual plans and budget
PP: Preliminary Plans - architectural
ASF: Square footage from the inside of wall surfaces within an assigned space.