Science and Technology Center Project Overview:
The new Science and Technology Mall will provide an appropriate complement of physical and life science labs, computer science labs, and computer art labs to meet the college's present and future needs. It will also house two independent learning labs, one a Basic Skills Training Center and the other a Biochemical Instrumentation Lab to suppport the physical and life sciences. The building will be located adjacent to the existing classroom and lab "core" of the campus where utilities and other support services are close at hand.
   
   
Project Description:
Project Name: Science and Technology Mall
Building S.F.: 59,668 GSF / 38,568 ASF
Total Labs/Classrooms: 10 Classrooms / 11 Labs
Gross Seats: 770 seats
Funding: State and local Prop R
Project Type: New Construction
Project Cost; $25,091,882
 
   
Project Team:
Program Manager: Joe Minner
Senior Project Manager: Erik Reuter
Project Manager: Aaron Golde
Architect: Spencer Hoskins Associates
Construction Manager : Rudolph & Sletten
 
   
Project Team:
IPP  
Board Approval:
Completed
State Approval:
Completed
FPP  
Board Approval:
Completed
State Approval:
Completed
PP  
Board Approval:
Completed
State Approval:
Completed
WD  
District Approval:
Completed
State Approval:
Completed
Issue for Bid
Completed
Construction  
Start:
July, 2005
Complete:
January, 2007
 
   
Legend:
IPP: Initial Program Proposal - programming
FPP: Final Program Proposal - conceptual plans and budget
PP: Preliminary Plans - architectural
ASF: Square footage from the inside of wall surfaces within an assigned space.
GSF: Square footage of the entire building to the outside of all the walls.
WD: Working Drawings
 
     
 