Project Overview:
The Digital Arts Laboratories Building will include a wet photography facility and its digital counterpart; the digital counterpart of traditional art labs; a digital multimedia lab designed to merge the traditional fine arts, music, video and cinema; media labs, including the KGFN campus radio station and a video studio; and faculty offices. The Sculpture Laboratory Building and Yard will provide sculpture and 3-D design/jewelry studios with a large outdoor sculpture work yard.
   
   
Project Description:
Project Name: Digital Arts / Sculpture Complex
Project S.F.: 26,873 GSF / 18,466 ASF
Total Labs/Classrooms:  
Funding: State and Prop. R funded
Est. Project Cost: $17.5M
 
   
Project Team:
Program Manager: Joe Minner
Project Manager: Jim Davies
Architect: Mosher Drew Watson Ferguson, Architects
Construction Manager: Sundt Construction, Inc.
 
   
Project Team:
IPP  
Board Approval:
Completed
State Approval:
Completed
FPP  
Board Approval:
Completed
State Approval:
Completed
PP  
Board Approval:
Completed
State Approval:
Completed
WD  
District Approval:
Completed
State Approval:
Completed
Issue for Bid Completed
Construction  
Start:
September 2005
Complete:
January 2007
 
   
Legend:
IPP: Initial Program Proposal - programming
FPP: Final Program Proposal - conceptual plans and budget
PP: Preliminary Plans - architectural
ASF: Square footage from the inside of wall surfaces within an assigned space.
GSF: Square footage of the entire building to the outside of all the walls.
WD: Working Drawings
 
     
 

Digital Arts Building



Sculpture Arts Building




|




|

Campus Overview:


 

 

 
Contact Us | Disclaimer