Grossmont Science Lab Building
 
Science Lab Building Project Overview:
This two-story building, houses laboratories for biology, chemistry, and geology/oceanography programs, as well as storage facilities, faculty offices, a 40-station computer learning center, a greenhouse facility and an exterior native garden. The placement of the facility completes a square of four buildings – the Science and Technology quadrangle – surrounding a large open space.
   
   
Project Description:
Project Name: Grossmont Science Building
Building S.F.: 37,834 GSF / 26,315 ASF
Total Labs/Classrooms:  
Funding:

State general obligation bonds and
Prop R

Est. Project Cost: $19.7M
 
   
Project Team:
Program Manager: Joe Minner
Project Manager: Jim Davies
Architect: Spencer/Hoskins associates
Construction Manager: CW Driver
 
   
Project Team:
IPP  
Board Approval:
Completed
State Approval:
Completed
FPP  
Board Approval:
Completed
State Approval:
Completed
PP  
Board Approval:
Completed
State Approval:
Completed
WD  
District Approval:
Completed
State Approval:
Completed
Issue for Bid Completed
Construction
Phase 1 completed
Start Phase 2:
Spring 2005
Complete:
October 2006
 
   
Legend:
IPP: Initial Program Proposal - programming
FPP: Final Program Proposal - conceptual plans and budget
PP: Preliminary Plans - architectural
ASF: Square footage from the inside of wall surfaces within an assigned space.
GSF: Square footage of the entire building to the outside of all the walls.
WD: Working Drawings
 
     
 